Q: What is a DIC4306 Boiler Data Report?
A: The DIC4306 Boiler Data Report is a report used to record the results of the first internal inspection of a boiler.
Q: When is the first internal inspection of a boiler required in Ohio?
A: The first internal inspection of a boiler in Ohio is required within three years of initial operation, or after 1,000 operating hours, whichever comes first.
Q: Who is responsible for conducting the first internal inspection?
A: A qualified boiler inspector, authorized by the Ohio Department of Commerce, is responsible for conducting the first internal inspection.
Q: What information is recorded in the DIC4306 Boiler Data Report?
A: The DIC4306 Boiler Data Report records information such as boiler identification, inspection date, observations, corrective actions, and the inspector's signature.
Q: Is the DIC4306 Boiler Data Report required to be submitted to any authorities?
A: Yes, the DIC4306 Boiler Data Report must be submitted to the Ohio Department of Commerce within 30 days of the inspection.